Monday: We met with another (#4) excavator. Stu likes him and they seem to be on the same page as far as what needs to/should be done. And look at that grass! Too bad most of it will be dug up again, but for now it looks good.
Tuesday: We were all set for an epic workday! We were supposed to have 2 trucks making 2 trips with the blocks for our retaining wall... Well, we ended up with 1 truck and only 1 trip. But at least it's a start.
Loading the truck.
Unloading...
Our haul for the day.
Today we met with the representative from the electric company with our drawings/maps/instructions to get the lines run to the property.
We have hurricane Zeta coming in, it's been raining all day today and we're in for 2 more days of it. We are scheduled to get more blocks on Monday but it may be too muddy. Should be a nice sunny weekend though, so we'll see....